WET-END NOTE 07 / TROUBLESHOOTING

Paper Machine PAM Troubleshooting Guide

Diagnose papermaking PAM retention, drainage and formation changes through furnish, make-down, addition, shear and white-water evidence.

FURNISH
actual stock
ADDITION
defined sequence
EVIDENCE
measured sheet
Automated polyacrylamide make-down and wet-end dosing system in a paper mill
WET-END NOTE 07 / TROUBLESHOOTING

Published · Updated · Gongyi Xinqi Polymer Co., Ltd.

SHEET INDEX01Preserve the current state02Verify product and batch03Inspect solution preparation04Check dosing hardware05Review furnish and charge06Trace addition and shear07Run a controlled check08Close the corrective record09Carry the machine evidence into purchasing10Machine-trial record
01

Preserve the current state

Record grade, furnish, speed, chemistry, feeder outputs, white water, retention, drainage and paper defects.

Avoid changing several additives before a baseline is captured.

02

Verify product and batch

Check product code, lot, packaging condition and receiving record against the approved identity.

Confirm that no unqualified substitution occurred.

03

Inspect solution preparation

Review dilution water, concentration, feeder calibration, wetting, aging, deposits, tank turnover and solution age.

Incomplete hydration can look like low product activity.

04

Check dosing hardware

Confirm pump output, pulsation, blocked lines, calibration, dilution flow and injection quill condition.

Use a measured drawdown or flow verification when possible.

05

Review furnish and charge

Compare fines, filler, broke, conductivity, pH, cationic demand and contaminant sources with the accepted baseline.

Process change may be the real cause.

06

Trace addition and shear

Confirm injection point, mixing, contact time and approach-flow equipment status.

A screen, pump or flow change can alter floc survival.

07

Run a controlled check

Repeat blank, incumbent or retained reference tests with representative stock and active addition.

Change one cause at a time.

08

Close the corrective record

Document root cause, verified correction, restored metrics and any new control limit.

Retain the record for future lot and process comparisons.

09

Carry the machine evidence into purchasing

Use the demonstrated furnish, preparation and measurement window when reviewing Paper Retention CPAM Powder or Emulsion: Compare the Preparation Scope; Papermaking PAM First-Lot Acceptance: Match the Shipment to the Trial; Changing a Paper PAM Supplier: Plan the Crossover Around Grade and Loop Stability.

Retain the accepted sample identity, quality gates and unresolved conditions with the quotation. A product or process change should receive the relevant review before it becomes part of routine supply.

10

Machine-trial interpretation and release record

Start with a dated baseline and fault timeline. Place delivery lots, solution batches, feeder or pump work, furnish changes, broke return, water changes and machine events in one sequence. Mark the first measured deviation rather than the time an operator reported it. A sudden response after maintenance may have a different explanation from gradual deterioration during a changing furnish campaign.

Use paired current-stock comparisons to separate competing causes. Prepare the current material and a retained accepted reference with the same water, concentration, age and method. Check calibration and addition hardware before assigning a viscosity or retention difference to product quality. Keep all sample and solution labels connected so an investigation does not compare unrelated stock or misidentified preparations.

Verify the suspected correction by returning to a documented reference condition and repeating the relevant paper and process measurements. Do not leave a higher feed setting as the permanent solution unless its active basis and complete quality balance are justified. Preserve the cause, evidence, corrective action and review trigger with the operating record. If a supplier concern remains, send lot documents, storage and preparation history, current stock conditions and paired results. A structured comparison supports a responsible material decision without assuming in advance that either the mill process or the supplied polymer must be at fault.